Trusted Experts in Urban Reconstruction
Explore our signature projects that reflect innovation, skill, and our commitment to quality in construction and engineering.

Location: Baghdad Governorate – Abu Nawas Street
Rehabilitation and development of the Rafidain Bank building (General Administration)

Location: Baghdad Governorate
Rehabilitation works of the protective fence of Mohammed Al Qasim Bridge

Location: Baghdad Governorate
Development and rehabilitation of the northern entrance to Baghdad (Baghdad – Mosul) with a distance of 33 km

Location: Baghdad – Asia Neighborhood Complex
Construction of 3 residential buildings with a commercial complex

Location: Baghdad
Establishment of a commercial complex and parking lot

Location: Baghdad Governorate – Zayona
Establishment of a cafeteria, café, and parking lot

Contract for the implementation of the Southwest Transmission Line and its two pumping stations SW1, SW2
Such as rehabilitation of gas unloading and compressor stations, repair of water injection stations, rehabilitation of gas separation and liquefaction plants, rehabilitation of gas pipeline tanks, cooling and loading plants, construction works for gas and oil pipeline networks, supply and installation of high voltage electrical switches, and construction works for asbestos for water lines.

Rehabilitation and development project for the Mohammed Al-Qasim Expressway in Iraq
The project includes the development of the Mohammed Al Qasim Expressway with a length of (20) km, including intersections, and its conditions for the works include the application of natural and artificial stone from international sources, and also includes the planting and cultivation works for the side walkways and sides, and the maintenance of the road in general.

Contract for the implementation of a main sewer line using the concealed excavation method
Al Khiran Company is currently implementing a strategic project to construct a main sewer line using concealed excavation technology on Port Said Street, in coordination with relevant authorities. The project aims to develop the sewerage network infrastructure without disrupting traffic or the daily lives of residents. It utilizes modern technologies that enable the pipes to be laid underground without the need for open excavation. The project also includes the construction of two main pumping stations to ensure efficient water flow and effectively address environmental challenges. This project serves as a model for leveraging technology to serve infrastructure in a sustainable and safe manner.
Projects:
- 1958 Paving of the internal roads of the housing project in western Baghdad (Al-Washash area) in cooperation with the municipality at the time.
- 1959 Paving of the internal roads of the officers’ residences in the Zayouna area (Baghdad, towards Rusafa) with sidewalks in cooperation with the municipality.
- 1963 Paving of the internal roads of the then Amara District (currently Maysan Governorate) for the municipality.
- 1964 Paving of the internal roads of the city of Sulaymaniyah (Sulaymaniyah Governorate) for the municipality.
- 1968 Paving of the 9 km long (Amara-Majar) road for the sugar factory.
- 1970 Paving and sewerage of the internal roads of the Fallujah District (Anbar Governorate) for the municipality.
- 1972 Paving of the right side of the Kadhimiya-Taji road (Baghdad, towards Karkh) for the Roads and Bridges Department.
- 1975 Paving of the (Khanaqin – Bab Lawi Qulay) road and the (Khanaqin – Tabba villages) road, 90 km long (Diyala Governorate).
- 1976 Paving of the (Arbad – Halabja) road, 60 km long (Sulaymaniyah Governorate) for the benefit of roads and bridges.
- 1977 Implementation by turnkey method of the Rashid Military Sewerage.
- 1977 Paving of the internal roads of Al-Hussainiya District (Karbala Governorate) for the benefit of the Municipality.
- 1978 Paving of the roads of Kirkuk ammunition depots, with a total length of 60 km, for the benefit of military works.
- 1979 Paving of the roads of Abu Gharb Al-Shamali and Abu Gharb Al-Janoubi (Maysan Governorate) for the benefit of the Southern Oil Company (Maysan Oil Department).
- 1981 Paving of the (Kahla – Halfaya) road (Maysan Governorate) for the benefit of the Southern Oil Company (Maysan Oil Department) with a length of 60 km.
- 1981 Construction of 100 housing units for the Iraqi Army in Kirkuk.
- 1983 Paving of the internal roads of the Dabouni Farm, with a total length of 60 km (Wasit Governorate), under contract with the Turkish company Ozko Baytur, for the Ministry of Agriculture.
- 1984 Paving of the roads of the Saqlawiyah Farm (Anbar Governorate), under contract with the Turkish company Ozko Baytur, for the Ministry of Agriculture.
- 1984 Paving of the road leading from the main road to the residential complex, along with the internal roads of the complex (Saad 23 Project in the Al-Amiriya sub-district, Fallujah District, Anbar Governorate), under contract with the Korean company Hyundai, for the Ministry of Housing.
- 1984 Construction of a residential complex for the Iraqi Army in Maysan Governorate (Al-Amara).
- 1990 Construction of 50 housing units for the Ministry of Construction in Baghdad Governorate.
- 2004 Paving of the (Zalam – Khormal – Ahmed Awa – Bayara Taleela) road with a length of 38 km in (Sulaymaniyah Governorate, under contract with Kirkuk Contracting Company for the benefit of the Sulaymaniyah Roads and Bridges Department.
- 2005 Paving of the (Karbala – 20th Revolution Square) road in Najaf Governorate in both directions with a length of 11 km in each direction and a width of 11 m under contract with the Compliance Company for the Ministry of Municipalities and Public Works.
- 2005-2008 Construction of 500 housing units for the Babil Provincial Council in Babil.
- 2006 Paving of the Sirwan district with the (Sirwan – Khormal) road with a total length of 18 km for the Sulaymaniyah Roads and Bridges Department (Sulaymaniyah Governorate).
- 2006 Building a bridge in Babil Governorate.
- 2006 Paving of the internal roads of Abu Ghraib camp with a total length of 18 km under contract with Abdullah Awiz Al-Jabouri Company for the Iraqi Ministry of Defense.
- 2008-2009: Supply of 600,000 120-liter waste containers from the German company ESE (for the Baghdad Municipality).
- 2009: Supply of materials, installation, and operation of a 33 KV electricity project, and installation of 18 km of towers from the Nasiriyah power station to the Shamiyah power station.
- 2010: Turnkey slaughterhouses for cattle and sheep were implemented in Karbala and Anbar.
- 2010: Construction of 75 residential villas in Babil Governorate for the University of Babylon.
- 2010: Implementation of the Southwestern Conveyance Line project with its two pumping stations using the hidden excavation method “jack” for pipes, along with paving of the project’s roads for the Baghdad Municipality – Baghdad Sewerage Department. • 2011: Construction of Imam Ali Hospital in Baghdad (Sadr City).
- 2011: Supply of four asphalt plants and their accessories to the Ministry of Housing.
- 2011 Development (paving, adding green spaces, developing intersections, building parks, lighting) of the 22 km round-trip Mohammed Al-Qasim expressway (2011).
- 2011 Implementation of a 17 km main sewage line in the southwest of Karkh city, along with its two pumping stations.
- 2011 Supply of spare parts for the Baiji refinery in cooperation with the German company LLG.
- 2011 Supply, installation, and operation of a Korean “Spico” asphalt plant for Hammurabi Company in Diwaniyah Governorate.
- 2005-2012 Paving of more than 3 million square meters of roads throughout Iraq.
- 2012 Construction of 1,200 housing units in Baghdad/Al-Khar (an investment project by Baghdad Governorate).
- 2013 Supply of 1,500 Korean-made Daedong agricultural tractors for the Iraqi Ministry of Agriculture.
- 2013: Supply of more than 250 sewage and water pumps from the German company KSB for the Baghdad Municipality.
- 2014: Supply and supply of protection devices for power generation systems, along with providing training courses for the Maysan Electricity Directorate.
- 2016: Supply, installation, and operation of power generation devices for the electricity grid of the Al-Sajjad station, Maysan Governorate.
- 2017: Supply of materials, installation, and operation of a 33 KV electricity project, and installation of distribution towers for the new Amara station to and from the old Amara station, Maysan Governorate.
- Establishment of a huge commercial complex (Crystal Mall) in the center of the Jordanian capital, Amman, in partnership with Al-Balagh Company.
- A project to supply 4 power generators to the Iraqi Council of Representatives and a contract to supply their cables.
- 2017 – 2022
- Residential Complex – Dora, Baghdad
- Components: 3 residential towers
- Duration: 2017–2022
- Objective: To provide modern housing units with supporting amenities in the Dora district.
- 2021 – Present
- Commercial Mall Project – Zayouna, Baghdad (Ongoing)
- Area: 30,000 m²
- Components: Modern retail spaces, large green areas, and full service infrastructure.
- Objective: To create a comprehensive shopping and entertainment destination for the area.
- Al-Sadir Hotel Project – Baghdad (Ongoing)
- Area: 35,000 m²
- Rating: Five-star hotel
- Components: Landscaped green areas, casinos, fine dining restaurants, and an integrated shopping complex.
- Objective: To develop a luxury hospitality and tourism complex in the heart of the capital.
- 2023 – 2024 (Completed)
- Rafidain Bank Headquarters Building Project
- Status: Completed in 2024
- Objective: Constructed as a modern administrative headquarters that meets the latest banking standards and provides a fully equipped work environment.
- 2023 – Present
- Baghdad–Mosul Road Project (Ongoing)
- Length: 33 km
- Components: Approach roads, 4 main bridges, and route upgrades.
- Objective: To enhance connectivity between Baghdad and Mosul and improve transportation flow.
- Hotel Project – Street 42, Baghdad (Ongoing)
- Land Area: 2,000 m²
- Height: 10 floors
- Capacity: 106 rooms
- Objective: To build a modern hotel catering to business travelers and tourists.
- Bour Said Sewerage Project – Baghdad (Ongoing)
- Length: 2,670 m
- Execution Method: Trenchless technology
- Components: Main pumping and treatment station.
- Objective: To improve and expand the city’s sewerage network to serve new areas.
Their expertise and dedication truly transformed our project, exceeding every expectation.